Social Sciences and Mathematics Building
Construction Progress

Building Description
This page is maintained by Dan Smith, UVic Geography

HyperCounter
Visitors since May 1, 2006


February 18, 2008Furnishing up the building
February 14, 2008Touring the building
February 8, 2008Finishing up
November 30, 2007Before the rains
November 19, 2007Working around
November 18, 2007Working around
November 11, 2007Good fall weather for outside work
November 7, 2007Around and about
November 5, 2007Dropoff boxes and spaces
October 31, 2007The roof greens up
October 19, 2007Of sidewalks and things
October 5, 2007Looking at the big picture
October 2, 2007Outside activity
September 29, 2007Green landscapes on the roof
September 27, 2007Insider inside
September 19, 2007Looking good
September 17, 2007Stairways going up and down
September 10, 2007Cabinets are going in
August 27, 2007Sunshades are going on
August 15, 2007Inside and out
August 15, 2007Inside and out
August 1, 2007What is going on behind the fences?
July 12, 2007Putting the dirt on the roof
June 14, 2007Stairway to heaven?
June 13, 2007Quickening pace
May 25, 2007Craning around
May 23, 2007Under the roof
May 21, 2007Greening up the roof top
May 18, 2007South winging it
May 10, 2007Deck the hall
May 9, 2007Glimmering reflections
May 5, 2007Some colour and interior design
April 15, 2007Spring sunshine and a handsome structure
March 29, 2007Glulam breezeway
March 27, 2007Interior details
March 26, 2007Looking down
March 20, 2007Glassy future
March 7, 2007Framing up some outside walls
February 26, 2007Will not be long now
February 18, 2007The shell is almost finished
January 20, 2007The inside scoop
January 10, 2007More snow on the site
January 4, 2007Christmas break progress
December 16, 2006Progress despite a spate of wind storms
December 12, 2006Schematic of lobby area and staircase down to classrooms
November 30, 2006November snow slows progress
November 23, 2006Part 2. The view from on high
November 23, 2006Part 1. November rains rule
November 11, 2006Putting the pieces together
November 5, 2006November rains and the look of a building
October 21, 2006New floors and rooms showing up everywhere
October 16, 2006A slice through the building
October 12, 2006The big pour
October 7, 2006Filling in the floors
September 13, 2006Some interior action
September 7, 2006A pretty busy site
August 30, 2006You can start to imagine what it might look like
August 18, 2006Beginning to take shape
August 12, 2006Whole lotta action on the site
July 25, 2006Lot's of progress again this week
July 19, 2006South wing continues, North wing going up!
July 07, 2006Under slab preparations
June 30, 2006Large lecture theatres taking shape
June 23, 2006Getting things done in a hurry
June 16, 2006The walls keep going up
June 9, 2006Artist at work
June 4, 2006South wing begins
May 27, 2006Walling up
May 19, 2006Going high
May 12, 2006The Two Towers
May 7, 2006Lots more excavation
April 28, 2006The hole gets bigger
April 22, 2006Site excavation begins
April 14, 2006Closing of parking lot and clearing of site
March 2006Schematics of what the building will look like when finished
March 2006Building plans

Return to Index


        The move coordinators were given a tour of the building today and were able to see the progress made. Furniture is being constructed and last minute painting is underway.

Link to a Photo Album showing some inside spaces

Return to Index


Return to Index


Return to Index


Return to Index


Return to Index


Return to Index


Return to Index


        The roof tops are taking on a very different look following the sprouting of greenery and additional steel framework over the south wing stairway.

Return to Index


        Around the building the sidewalks are being finalized and the

Return to Index


        The exterior views of the south and north wings of the building emphasive that the former is a few weeks ahead in terms of overall progress.

Return to Index


        Finishing work continues around the building perimeter, with the entrance ways on the south wing progressing quickly.

Return to Index


        The beginnings of greening the building roof are underway. Some of the trees have been planted and pathways built.

Return to Index


        The SSM Bldg is racing forward, with some interior rooms in the south wing appearing almost ready for occupancy. There are cabinets and cupboards in some rooms, and the hallways have an almost what-it-will-look-like feel to them.

Return to Index


        The exterior of the building looks almost complete from some angles. From others it is clear that a few finishing touches are still underway.

Return to Index


        Work is underway to complete the exterior staircases at several locations around the building. The staircase leading down from the David Strong Building to the interior courtyard looks to provide a floating entrance this green-filled space.

Return to Index


        Inside the building finishing work is underway. In the south wing cabinets are being installed in the third floor undergraduate physical geography teaching laboratory.

Return to Index


        Work is progressing rapidly on placing the exterior facade and sunshades on the southern wing of the building.

Return to Index


        The exterior facade has acquired some colour and is providing a clue as to what the final appearance of the building will be. The trench and sidewalk configuration along the southern exposure of the south wing are being finished, and the sidewalks are being poured along the pedestrian pedway between the new building and the Strong Building. Inside the SSM Building the interior stairway under the pine beams is in place and the hallway cladding is providing a natural feel.

Return to Index


        The roof top growing medium is now in place.

Return to Index


        Work on the SSM Building continues at a hurried pace - hastened by the excellent weather. Expanded fencing around the site makes it harder to see the changes going on inside, but the exterior facade is progressing rapidly and the structure is getting a far more finished look than even a few weeks ago.

Return to Index


        Hidden from view up on the roof tops, workers have been setting up the beds for the green roofs. Although no plantings will occur to later in the year, it was important to lift the soil up there while the construction crane still loomed over the site.

Return to Index


        The framework for the sprial staircase in the south wing has now been installed. Visible from the interior courtyard through a three storey sheet of glass, the staircase is bound to provide an exciting venue for slip sliding away.

Return to Index


        The pathways around the building have been closed and the pace of construction has intensified. The interior of the south wing has drywall in most places and the interior spaces have begun to take their final form. The spiral staircase will be put into place very soon and an example of the hallway panel board is up for viewing. The arched atrium area is in place and sets a grand stage for the building.

Return to Index


        The mystery of the framework that has puzzled so many is solved.

Return to Index


        The signature feature of the SSM Building so far has to be the beautiful curved pine beams that grace the courtyard atrium area. As the building gradually is sealed up it is becoming harder and harder to imagine what the inside spaces are going to look like. Today's image suggests the atrium area is destined to be a popular gathering place.

Return to Index


Return to Index


        The south wing is really looking finished from the outside. A good piece of the drywalling inside is now finished and the 'rockets' are beginning to find their way to the roof. The decking on the atrium area has extended out into the vicinity of the staircase down into the interior courtyard.

Return to Index


        The beetle-stressed wood ceiling decking has been installed above the curved lobby beams.

Return to Index


        The curtain wall in the south wing of the building is set to reflect the landscape and should provide for a restful stroll between buildings.

Return to Index


        The south wing of the building is starting to have a finished look. Lots of glass and windows, and the first suggestions of exterior colours. Over the last week or so a substantial amount of excavation has lowered the interior courtyard level. The curved beams that will support the glassed in gathering place provide some well-needed visual contrast.

Return to Index


        The windows are starting to fill in the open exterior walls in the south wing, giving the building a more finished look. Interior stud walls continue to appear everywhere and are being accompanied by the lacing of wires/cables. The pine beetle beams that support the breezeway and building atrium are slowly being put into place and are providing some well-deserved drama to the evolving concrete structure of the SS&M Building.

Return to Index


        The Glulam support beam for the breezeway entry into the building courtyard was installed today, providing a hint of the dramatic entryway still to come.

Return to Index


        All of the glue laminated beams are now in place. The north wing of the building is pretty well complete and windows are now defining the south wing. Some interesting looking structures are in storage on one side of the building

Return to Index


        Lots of work going on in the courtyard, with the first glue laminated beam put into place today.

Return to Index


        Most of the building structure is now in place. Inside the building the stud work for the rooms is keeping pace and glass is starting to fill in some exterior walls.

Return to Index


        The concrete framework of the north wing is quickly being finished off. Over in the south wing the framing for the exterior facade is starting to fill in and provide a hint of the general building appearance.

Return to Index


Return to Index


        A lot has been happening at the building site and the majority of the concrete structural work is now finished. Backfilling has begun around parts of the basement area and cladding is starting to appear at various places around the external structure. The interior of the building is gradually being framed. The central quad is beginning to look like a nice place to catch a few sunny rays on warm spring days. Bring on the espresso vendor.

Return to Index


        A chance to walk around the inside of the building on a busy construction day provided insights into the overall progress at the site. With a little imagination one can start to imagine some of the interior areas and to appreciate that, although the building looks small from the outside, the sense inside is one of flowing spaces. The department offices all look great and the various laboratories allow for lots of science opportunity.

Return to Index


        Another snowstorm hits the building site but everyone keeps on working. There is visible progress all over with the roof now in place on the eastern end of the southern wing. The large support beams put in place on the bottom floor of the south wing while the cement cured are now being removed, providing a good perspective on the size of each room.

Return to Index


        Construction work at the building site continued over the Christmas break. The building continues to grow upward at a pace that rivals the interior work going on at the same time.

Return to Index


        Over the past week three wind storms have blown through Victoria. Despite this work on the site has continued. Week-by-week the building grows in stature and form. Most of the basic shell of the south wing is now in place and the higher north wing has begun to extend upwards.

Return to Index


        A creative perspective of what the staircase and lobby view will look like in the classroom area of the north building wing. Note the planned for non-structural wood accents. The hope is to use some mountain pine beetle killed trees and create laminates to enhance the warmth of the building.

Return to Index


        Record breaking temperatures and lots of snow slow progress down. Despite the weather some progress was made over the last week.

Return to Index


        Part 2. Ever wonder what it looks like looking down from the construction crane at the building site? Cool.

Return to Index


        Part 1. Persistent rain continues to dampen the site but has barely slowed the construction activity down. Backfilling against the foundation has begun in some places around the building.

Return to Index


        November rains are ensuring that the mud is slick and the pools of water on the site more permanent. All the pieces are starting to go together quickly. Although they are still pouring concrete for the third floor in the south wing, down on the basement level the wall studding is starting to frame out some of the spaces. The beginnings of the central hallway on the basement level give a good impression of what this floor might look like.

Return to Index


        Heavy rain over the last couple of days has flooded some of the site. Despite this great progress is being made on the structure, with about two-thirds of the concrete now in place. The building is pushing skyward and some interior wall studding is already in place.

Return to Index


        The building complex is really starting to have a presence on the site as the two wings of the building grow out of the ground. A look inside at the courtyard that will separate the two areas provides a glimmer as to how this space might look. The lengthening mid-day shadows also give you a sense of how the building is likely to change the character this corner of campus. The walls of the Geography Department main office are being formed, with the office staff already running work place scenarios.

Return to Index


        An architectural rendering of the interior courtyard entrance to the classroom atrium area. Shown is a portion of the south-facing north wing and a slice through the classrooms in the atrium.

Return to Index


        It was an exciting week on the site. Over the long weekend there was a lots of activity as a bevy of construction works finished preparing the second floor on the north wing for a massive cement pour. This action was repeated on Thursday when a whole lot of people were involved in pouring the second floor of the south building. Looks good, except that no one asked any geographers over to sign their names in the cement before it hardened.

Return to Index


        The building is starting to grow in stature and the overall form is becoming clear to all. Right now the building is a bit castelled in appearance and it takes a bridge to get onto the second floor of the building. In the western corner of the north wing the beginings of the third floor are starting to appear. The second story floor on the eastern section of the south wing is about ready to set and there is some indication of how the sunshades over the physical geography laboratories are going to shape the building appearance.

Return to Index


        Lots going on inside the structure as the lecture rooms begin to take shape and the basement floors filled in. Takes a lot of temporary support to hold up the floor above for a cement pour.

Return to Index


        There is a lot going on at the moment. All the exterior basement walls are close to completion and the attention now seems focused on forming up the interior walls in the core of the building. Work also continues on getting the basement floors ready for finishing, with gravel being packed down on top of the buried services. Visible is the loading bay door opening that leads into the secure storage area,

Return to Index


        The basement portion of the building is beginning to look a lot more complete. With the addition of some interior walls, doorways and pillars, it is now easier to imagine how the structure will work. Progress remains on track and most of the basement area now seems to be in place. Lots of activity focused on getting the forms in place to make serious headway on the next floor up and to getting the pipes in place before pouring the basement floor.

Return to Index


        A good portion of the basement is now being finished off, with the outer membrane and sealant in place. Workers are continuing to build the forms for the walls in the offset portion of the south wing and have begun the process of pouring the second floor in the north wing. Drilling through the shear walls in the south wing is underway prior to the basement floors being poured.

Return to Index


      Over the last few weeks a lot has been accomplished. Most of the shear walls in the south and north wings are now completed. The physical geography labs in the basement of the south wing can now be imagined, with progress being made in tamping gravel down prior to the floor slabs being poured. The construction crew is quickly digging out and framing up the offset portion of the south wing. Over in the large lecture theatre in the north wing floor anchors for the lecture seats are now established.

Return to Index


      It takes a lot of preparation to cast the floor! The formwork is in place for Geography's Spatial Sciences and Geomatics wing. Next step is to lay out the in-slab conduit and plumbing.

      Lot's of steel is placed in the columns and sheer walls. This pic shows a doorway being formed in the shear wall between the SPECTRAL Lab and it's darkroom.

      The large lecture theatres will be completely underground. The berm along ring road will slope over the lecture theatres up to the first row of vertical re-bar, left of centre in the photo.

Return to Index


Return to Index


Return to Index


Return to Index


Return to Index


    Word on the street has it that if the weather continues to cooperate, and if the University continues to receive tenders that are within their budget estimates, and if local tradespeople continue their high productivity and if the site continues to be accident and mistake free, then it is feasible that by the end of August the lower level of the building will be complete to the point that backfilling can commence. If that happens, then the access routes along BEC/Strong and along Sedgewick might be full width before classes resume in September.During the three summer months, there will lots of formwork, re-bar placement and concrete pouring. Followed by the installation of mechanical and electrical systems.

Return to Index


    Rainy weather has not slowed down the activity at the site this week. The foundation walls on the north side of the building continue to grow upwards and around the site. The excavator operator continues to demonstrate his artistry and is carving forms out the stiff clay into which the concrete is poured for the foundation.

Return to Index


    Serious concrete pouring has helped to shape the basement wall along the north wing of the building where the large lecture theatres are going to be. Progress has been made in the eastern corner of the south wing adjacent to the Cornett Building where the physical geography labs will be located. Thanks to some rain over the last week the site is little muddier than it has been to date.

Return to Index


    Losts more digging and the forms for the northern basement walls begin to take shape. So far the crane hasn't played a major role on the site, with the excavator and the dump trucks continuing to be the most prominent feature. Lots of time being spend wiring rebar together.

Return to Index


    The beginning of the week saw the theatrics of crane construction completed. Lots of high wire activity and the first real perspective on the scale of the building. Excavation started again along the perimeter of the site where the south wing will be located. Along the north edge of the site footings continue to be built simply by carving a hole in the clay and filling it with concrete. Concrete forms are being constructed for the foundation walls.

Return to Index


    Construction activities increased in intensity this week. Footings along the eastern wall of the north wing (lecture theatre country) have been put in place and some of the rebar for the foundation walls has been set. More exciting was arrival of the large truck-mounted crane which is being used to build the construction crane soon to dominate the site. As all of this activity is happening right beside the pathway and almost everyone pauses to have a look.

Return to Index


    The excavation for the building just gets bigger and bigger with a continuous stream of trucks rumbling their way off campus. For those wondering, the excavated clays are headed to the Hartland Landfill where they provide a wonderful sealer for the daily accumulation. A pad for the construction crane has been poured and is now curing prior to the crane being erected. Confused rabbits wander around the contruction site, as does the professor who admits to having parked his car in Lot D some 100,000 times.

Return to Index


Return to Index


Return to Index


    Parking Lot D is closed and clearing of the site begins. Lights are taken down and the landscape trees removed. A temporary pedestrian walkway is established adjacent to the Sedgewick Building.

Return to Index


    Below are some schematic illustrations of what the new building will look like when completed. Note the impact of climate change by 2007 on the Victoria landscape!

Return to Index


    Links are to working versions of the floor plans and space allocations for the various department in the building.
  • First floor
  • Second floor
  • Third floor
  • Fourth floor
  • Fifth floor
  • Return to Index


    If you wish to receive announcements about photograph updates and other department news, you are invited to join UVic-Geog
    .

    Return to the Department of Geography Homepage